"水利部门","不同行政区域边界水工程批准","15个工作日",,
,"文化部门","市级文物保护单位保护措施、保护工程及有关事项许可审批","13个工作日",,
,"气象部门","重点水利工程项目气候可行性论证","备案",,
,,
"林业部门","建设项目使用林地及在林业部门管理的自然保护区建设审批","20个工作日",,
,"文化部门","配合建设工程的考古调查、勘察方案审核和抢救性发掘许可审批","13个工作日",,
,"林业部门","森林公园占地审查","20个工作日",,
,,
"国土房管部门","解除建设项目压覆重要矿产资源审批","13个工作日",,
,"地震部门","影响地震观测环境的新建、扩建、改建建设工程审批","10个工作日",,
,"国土房管部门","建设项目压覆重要矿产资源审批","20个工作日",,
,,
"交通部门","港口岸线使用审批","20个工作日",,
,"中介服务","建设工程地震安全性评估","备案",,
,"交通部门","跨越(穿越)公路或者与公路接口等事项的初步设计审查","7个工作日", ,,
"国土房管部门","地质灾害危险性评估审查","7个工作日",,
,"区县政府","小型水利工程征地移民安置规划大纲审批","内部事项",,
,"城管部门","国家级、市级风景名胜区内重大工程项目选择方案核准审批","15个工作日",,
,,
"水利部门","洪水影响评价审批","15个工作日",,
,"水利部门","取水许可审批","15个工作日",,
,"水利部门","江河、湖泊新建、改建或者扩大排污口审核","15个工作日", ,,
"气象部门","避免危害气象台站气象探测环境审查","10个工作日",,
,"规划部门","核发建设用地规划许可证","局审18个工作日;
区审15个工作日",,
,"农业部门","国家级、市级涉水生物保护区影响专题评价(论证)报告审查","10个工作日",,
,,
"水利部门","一般水文测站设立或调整审批","15个工作日",,
,"水利部门","专业水文测站设立和调整审批","15个工作日",,
,"水利部门","围垦河道审核","15个工作日", ,,
"林业部门","工程建设占用湿地公园审查","20个工作日",,
,"规划部门","核发建设工程规划许可证","市审18个工作日;
区审15个工作日",,
,"航道主管部门","航道通航条件影响评价审核","20个工作日" ,"备注:建设用地规划许可证、建设工程规划许可证、洪水影响评价审批、取水许可审批、江河湖泊新建改建或者扩大排污口审核、一般水文测站设立或调整审批、专业水文测站设立和调整审批、围垦河道审核在工程开工前办理完成即可. ,"水利工程建设施工许可阶段选择性办理事项"水利工程竣工验收阶段选择性办理事项" ,,
"海事主管部门","通航水域水上水下活动许可","15个工作日",,
,"林业部门","林业采伐许可","10个工作日"水利部门","截流阶段验收","10个工作日",,
,"水利部门","下闸蓄水阶段验收","10个工作日",,
,"规划部门","建设工程竣工规划核实","局审18个工作日;
区审15个工作日",