编辑: bingyan8 2019-07-07

"福州市闽江下游防洪工程建设公司","福州市水利局","延期一年完工" "3","闽江北港南岸南江滨休闲路(排涝及护岸部分)","仓山区","本工程由胜利水闸加高加固.新建水闸5座,新建泵站2座和约8.113km长的护岸.","2008-2015","43000","2000","176","176","0.088","C1~C3标防洪堤已建成堤身主体,C4标防洪堤身已达防洪高程",,

"福州市闽江下游防洪工程建设公司","福州市水利局", "4","福州市闽江北港南岸防洪工程(壁头~乌龙江大桥段)","仓山区","新建堤总长7.6km;

新建3座排涝站(闸).","2012-2016","80546","17000","1529","1529","0.0899411764705882","C

5、C6标段约2.7公里防洪堤、清富水闸土建、C4马杭洲水闸土建、马杭洲主泵房土建施工已完成,C3标己交地部分填筑到7.3高程,C

1、C2正在进行堤身填筑及梁厝闸站桩基施工.",,

"福州市闽江下游防洪工程建设公司","福州市水利局", "5","福州市魁岐排涝二站工程","台江区","排涝站一座,设计流量80立方米/秒","2011-2015","23071","2300","192","192","0.0834782608695652","泵站主体土建施工完成,进行水闸泵站施工",,

"福州市闽江下游防洪工程建设公司","福州市水利局","延期一年完工" "6","闽江防洪工程福州段(一期琅岐段)","马尾区","新建堤防7734米、水闸3座、排涝站2座及管理房等配套工程.","2013-2016","41624","8000","670","670","0.08375","土方开挖及清表:7000m,22.5万方;

堤防垫层:6500m,18.8万方;

抛石:7000m,26万方;

袋装碎石:4300m,1.3万方;

土工布:4800m,19.5万平方;

排水板:5500m(桩号),126万米;

堤身砂:4900m,16万方.上道水闸主体基本完成;

芦沙、沃头浦闸站正在进行上部结构施工.",,

"福州开发区水利建设发展有限公司","马尾区政府", "7","连江县敖江流域下游防洪排涝工程","连江县","防洪堤6.72km,水闸4座排涝泵站2座,内河8条总长10.437km.","2013-2018","159000","3600","500","500","0.138888888888889","幕浦河、财溪河已完成工程量90%,牛村河整治已完成招投标,崩溪防洪堤加固改造正在开展招投标工作,牛村、新亭排涝泵站等工程已完成招投标等前期工作.",,

"连江县兴利水利投资有限公司","连江县政府",,

,,

"8","可门港经济开发区下宫片排涝工程","连江县","整治8条内河,总长3.747km,新建3座排涝闸","2013-2016","7800","1200","100","100","0.0833333333333333","C1标段正在招投标,目前主要是征地、赔青等前期工作",,

"福州可门港经济开发区管委会","连江县政府", "9","可门港经济开发区(大官坂片颜岐溪、象纬溪)防潮排涝工程","连江县","整治内河3条长3.549km","2013-2015","4800","1800","250","250","0.138888888888889","基础开挖及底板施工",,

"福州可门港经济开发区管委会","连江县政府", "10","罗源湾开发区金港工业区防洪排涝工程","罗源县","新建排洪渠长7009米,加高培厚排洪渠长996.126米,滞洪区防洪堤3437.472米,排水沟防洪堤2364.211米,截洪沟长7927米,改扩建排洪闸1座,排涝站1座等.","2009-2017","26500","2400","200","200","0.0833333333333333","已建成燕窝新水闸、土港排洪渠、亿鑫排涝站.正在建设可湖排洪渠两岸加高工程、岐佃排洪渠工程.",,

"罗源湾开发区管委会","罗源县政府", "11","罗源湾开发区松山片区大小获片防洪排涝工程","罗源县","大小获防洪堤总长约15620米;

下载(注:源文件不在本站服务器,都将跳转到源网站下载)
备用下载
发帖评论
相关话题
发布一个新话题