, "榆林市2019年重点建设项目1-4月份进展情况表(按推进单位分) 单位:万元" "序号","项目名称","投资主体","控股企业全称","企业属性","建设地点","建设内容及规模","建设起止年限","总投资","截至2018年底完成投资","2019年计划",,

"审批情况","2019年进展情况",,

"开工累计完成投资","存在或需协调解决的问题","开复工时间","是否建成","开复工个数","建成个数","市级包抓领导","项目推进责任单位","市直行业主管部门","备注" 年度投资","主要工作任务或建设内容",,

"1-4月份完成投资","建设形象进度及相关手续办理情况" "

九、佳县推进重点建设项目18个"312420","53680","174544",,

"0","18277",,

"71957",,

,,

"6","0",,

,,

"

(一)续建项目6个"171700","53680","98500",,

"0","7161",,

"60841",,

,,

"3","0",,

,,

"187","佳县方塌50MW风电项目","佳县大华新能源开发有限公司","陕西建工集团新能源有限公司","省属企业","佳县","50MW风电机组","2018-2019","45000","5000","40000","建成投运","已核准","3000","已复工,共需临时用地400亩,永久用地28亩,已累计完成征地约300亩.

正在进行升压站综合楼基础施工,永久林业手续已办理,计划11月份并网发电","8000","无问题","3月",,

"1",,

,"佳县政府","市发改委","", "188","佳县乌镇50MW风电项目","榆林国能新能源有限公司",,

"市域企业","佳县","50MW风电机组","2018-2019","44800","18000","26800","建成投运","已核准","888","已取得林业永久批复,用地报批手续正在办理.","18888","①征地难度大;

②与长庆管线有交叉;

佳县政府","市发改委","", "189","佳县东方红文化产业园","政府",,

"政府","佳县","占地面积99亩,建筑面积82.5亩.建设东方红纪念馆、东方红阁(布展)、东方红广场、陕北民俗展览馆、旅游扶贫产业一条街、红色大舞台、沿黄路停车场及上山步道等","2013-2020","50000","26480","4000","完成东方红纪念馆、陕北民俗展览馆、旅游扶贫产业一条街一期工程;

建成红色大舞台;

东方红阁完成布展",,

"0","1月份到位资金600万元,预计5月初开工","26480","①资金短缺,需协调扶贫部分落实部分振南资金用于旅游扶贫产业一条街建设",,

,,

,,

"佳县政府","市文化和旅游局","", "190","佳县河口岔至凉水井公路","政府",,

"政府","佳县","路线全长29.136公里,其中佳县境内长8.02公里","2018-2019","13000","800","12200","建成通车",,

"2773","涉及佳县3乡镇6个村庄,全长8.5公里,由神木市对口帮扶资金投资建设,目前已完成项目红线用地征迁工作,混凝土拌合站、梁场、钢筋加工场、项目驻地建设,完成水下灌注桩基140米;

已取得林业永久批复,项目用地手续、复垦方案、环保评价正在办理中","3573","无问题","3月",,

"1",,

,"佳县政府","市交通运输局","", "191","佳县"一场两馆"建设项目","政府",,

"政府","佳县","体育馆建筑面积3092平方米、游泳馆3010平方米,标准化体育场1处","2018-2019","6000","500","5500","建成",,

"0","前期手续已办理完毕,具备开工条件,因机构改革,正在落实项目推进责任单位","500","①资金短缺,目前仅落实了480万元的补助资金②机构改革后项目法人单位发生变化",,