"" "工程量清单汇总表" ,,

,,

"" "工程名称:淅川县娃鱼河生态治理工程" "组号","分组工程名称"金额(元)" "一","分部分项工程费","","", "二","措施项目费"0" "三","计日工"0" "四","其他项目"0" "合计(A) "","",,

, "","",,

, "","",,

, "分类分项工程量清单表" "工程名称:淅川县娃鱼河生态治理工程" "序号","项目名称","计量单位","工程数量","单价(元)","合价(元)","主要技术条款编码" "壹","第一部分建筑工程","","0",,

,"" "一","娃鱼河治理工程","","0",,

,"" "

(一)","岸坡浆砌石防护工程","","0",,

,"" "1","岸坡土方开挖","m3","1057.

790625",,

,"" "2","岸坡土方回填","m3","360.1803125",,

,"" "3","Mu60M7.5浆砌块石挡土墙基础","m3","280.52015625",,

,"" "4","Mu60M7.5浆砌块石挡土墙","m3","622.0903125",,

,"" "5","聚氯乙烯泡沫板","m2","180.522",,

,"" "6","pvc排水孔","m","159.58",,

,"" "

(二)","合页坝工程","","0",,

,"" "1","合页坝主体工程","座","1",,

,"" "1)","建筑物土方开挖","m3","733",,

,"" "2)","建筑物土方回填","m3","75",,

,"" "3)","C30钢筋砼底板","m3","218.03015625",,

,"" "4)","C40二期砼","m3","10.380009765625",,

,"" "5)","C30钢筋砼闸墩","m3","69.4500390625",,

,"" "6)","C25钢筋砼铺盖","m3","76.43",,

,"" "7)","C25钢筋砼消力池底板","m3","134.75",,

,"" "8)","C15砼垫层","m3","63.6200390625",,

,"" "9)","钢筋制安","t","17.44",,

,"" "10)","平面钢模板","O","209.70015625",,

,"" "11)","Mu60M7.5浆砌石海漫","m3","96.310078125",,

,"" "12)","反滤土工布","O","53.75",,

,"" "13)","φ7.5排水管","m","129",,

,"" "14)","碎石垫层","m3","17.890009765625",,

,"" "15)","粗砂垫层","m3","41.0900390625",,

,"" "16)","橡胶止水带","m","13.25",,

,"" "17)","闭孔泡沫板","O","45.4200390625",,

,"" "2","供电设施工程","","0",,

,"" "1)","电线杆","根","2",,

,"" "2)","高压电缆(JKLYJ-10KV-3*50)","m","100",,

,"" "3)","低压电缆(JSB-3*35+1*16)","m","50",,

,"" "3","合页坝连接段工程",,

,,

, "1)","砌体拆除","m3","71.68",,

, "2)","Mu60M7.5浆砌石恢复","m3","71.68",,

, "3)","砼拆除","m3","16.6",,

, "4)","C20砼井壁","m3","55.4400390625",,

, "5)","井盖拆除及安装","个","40",,

, "6)","曲面钢模板","m2","448",,

, "4","河岸两侧局部段防渗处理",,

,,

, "1)","C30砼防渗面板","m3","200",,

, "2)","聚氨酯防水涂料","t","0.850000610351562",,

, "

(三)","生态补水工程","","0",,

,"" "1","土方开挖","m3","136.220078125",,

,"" "2","土方回填","m3","20.48001953125",,

,"" "3","余方弃置","m3","115.74",,

,"" "4","C20砼镇墩","m3","1.44000122070312",,

,"" "5","C20砼消力池底板","m3","76.8000390625",,

,"" "6","C30钢筋砼梁、柱","m3","9.1800048828125",,

,"" "7","钢筋制安","t","1.63000122070313",,

,"" "8","平面钢模板","m2","86.900078125",,

,"" "9","渡槽外壁贴大理石面板(高档带图案)","m2","139.150078125",,

,"" "贰","第二部分机电设备安装工程","","0",,

,"" "一","娃鱼河治理工程","","0",,

,"" "

(一)","生态补水工程","","0",,

,"" "1","潜水泵(65WQ30-10-2.2含安装费)","台","1",,

,"" "2","低压控制柜(含配件、安装费)","套","1",,

,"" "3","DN65镀锌钢管(实管、含安装费)","m","50",,

,"" "4","DN65镀锌钢管(花管,开孔率25%,含安装费)","m","32",,

,"" "5","DN65闸阀(含安装费)","个","2",,

,"" "6","90度DN65弯头(含安装费)","个","2",,

,"" "7","45度DN65弯头(含安装费)","个","1",,

,"" "8","30度DN65弯头(含安装费)","个","2",,

,"" "9","电缆(3*10+1*6)(含安装费)","m","400",,

,"" "10","集水槽(含安装费)","t","3.90000244140625",,

,"" "11","景观灯(15wLED通常防水灯带、含安装费)","m","32",,

,"" "12","钢筋防护网(含安装费)","t","0.100000076293945",,

,"" "

(二)","合页坝工程","","0",,

,"" "1","50kv变压器","套","1",,

,"" "2","低压控制柜(含配件)","台","1",,

,"" "3","15KVA补偿器","套","1",,

,"" "4","防雷接地装置","套","1",,

,"" "5","水尺","个","4",,

,"" "叁","第三部分金属结构设备安装工程","","0",,

,"" "一","娃鱼河治理工程","","0",,

,"" "

(一)","合页坝(坝长20.2m,坝高2.5m)","","0",,

,"" "1","金属结构设备及材料","","0",,

,"" "1)","闸门金属构件制作","m2","50.5",,

,"" "2)","制作钢板闸坝面","m2","50.5",,

,"" "3)","主液压缸(特制)","支","6",,

,"" "4)","液压泵站","台","1",,

,"" "5)","液压油","t","1",,

,"" "6)","液压管道及配件","套","1",,

,"" "7)","止水系统","m","31",,

,"" "8)","防腐","m2","156",,

,"" "9)","安装、调试服务费、检验费、二次搬运费","m2","50.5",,

,"" "肆","第四部分施工临时工程","","0",,

,"" "一","导流工程","","0",,

,"" "

(一)","娃鱼河导流工程","","0",,

,"" "1","岸坡河道围堰工程","","0",,

,"" "","土围堰填筑","m3","450.8003125",,

,"" "","编织袋堆筑","m3","36.34",,

,"" "","防渗土工膜","m2","210.68015625",,

,"" "","土围堰拆除","m3","487.1403125",,

,"" "2","桩号1+272~1+906东风渠渡槽至老街桥下游导流明渠工程",,

,,

, ,"导流明渠开挖","m3","3995",,

, ,"导流明渠回填","m3","3995",,

, "3","桩号2+212~2+428人民路上游至入内河口河导流明渠工程",,

,,

, ,"导流明渠开挖","m3","1361",,

, ,"导流明渠回填","m3","1361",,

, "4","合页坝围堰工程",,

,,

, ,"土围堰堆筑","m3","395",,

, ,"编织袋堆筑","m3","25",,

, ,"防水塑料膜","m2","164",,

, ,"土围堰拆除","m3","420",,

, ,"施工钢板围挡","m2","220",,

, ,"临时水泵(SLS125-100)","台","1",,

, ,"塑料软管","m","150",,

, "二","施工交通工程","","0",,

,"" "","砼路面","m2","480",,

,"" ,"15cm砂砾石垫层","m2","480",,

, ,"土方压实","m3","360",,

, "三","施工房屋建筑工程","","0",,

,"" "","施工仓库","m2","150",,

,"" "","办公、生活及文化福利建筑","%","1.5",,

,"" "四","其他施工临时工程","%","1",,

,"" "","其他施工临时工程","%","1",,

,"" "","合计" "材料预算价格汇总表" "合同编号:N0-0001" "工程名称:淅川县娃鱼河生态治理工程"单位:元" "编号","名称及规格","单位","预算价格","其中" 原价","运杂费","运输保险费","采购保管费" "1","低发泡沫塑料板","m2",,

,"0","0","0" "2","PVC管","m",,

,"0","0","0" "3","砂","m3",,

,"0","0","0" "4","汽油","kg",,

,"0","0","0" "5","粗砂","m3",,

,"0","0","0" "6","中砂","m3",,

,"0","0","0" "7","卵石20","m3",,

,"0","0","0" "8","铁件及预埋铁件","kg",,

,"0","0","0" "9","铁丝","kg",,

,"0","0","0" "10","块石","m3",,

,"0","0","0" "11","合金钻头","个",,

,"0","0","0" "12","碎石","m3",,

,"0","0","0" "13","碎石20mm","m3",,

,"0","0","0" "14","橡胶止水带","m",,

,"0","0","0" "15","电焊条","kg",,

,"0","0","0" "16","柴油","kg",,

,"0","0","0" "17","油毛毡","m2",,

,"0","0","0" "18","预制混凝土柱","m3",,

,"0","0","0" "19","塑料薄膜","m2",,

,"0","0","0" "材料预算价格汇总表" "合同编号:N0-0001" "工程名称:淅川县娃鱼河生态治理工程"单位:元" "编号","名称及规格","单位","预算价格","其中" 原价","运杂费","运输保险费","采购保管费" "20","复合土工膜","m2",,

,,

"0","0" "21","土工布","m2",,

,,

"0","0" "22","电","kw.h",,

,,

"0","0" "23","粘土","m3",,

,,

"0","0" "24","工程胶","kg",,

,,

"0","0" "25","风","m3",,

,,

"0","0" "26","钢筋","t",,

,,

"0","0" "27","水","m3",,

,,

"0","0" "28","编织袋","只",,

,,

"0","0" "29","空心钢","kg",,

,,

"0","0" "30","水泥32.5","kg",,

,,

"0","0" "31","水泥42.5","kg",,

,,

"0","0" "32","炸药","kg",,

,,

"0","0" "33","导电线","m",,

,,

"0","0" "34","电雷管","个",,

,,

"0","0" "35","非电毫秒雷管","个",,

,,

"0","0"