二、实施对象 2. Applicability 本通知适用于公司管辖范围内申请容量在160千伏安及以下的分散低压用电客户(批量报装的低压用电商业和房产项目及其他电压等级用电客户除外). This notice applies to scattered low-voltage consumers who apply for
160 kVA or less within the jurisdiction of the company (except for low-voltage electricity commercial use and real estate projects and other voltage-rate customers for bulk installation).
三、工作目标 3. Working goals 无外线工程的用户接入用时不超过5个工作日(全部为供电公司用时);
有外线工程但无需道路开挖的用户接入用时不超过20个工作日(全部为供电公司用时);
有外线工程且需道路开挖的用户接入用时不超过35个工作日(供电公司用时不超过20个工作日、政府用时不超过15个工作日).供电公司为客户接入工程实施主体,全程代办相关手续,为客户提供一站式服务.公司电网建设投资延伸至客户电能表,费用从公司业扩配套电网基建项目包或技改项目包中列支.低压客户报装涉及的所有环节审批权限和相关系统操作权限全部下放至供电公司,项目由供电公司审批并报公司备案,实现项目审批、计划下达和工程实施一个供电单位内流转.推行外线工程选线设计一体化和可研初设审批一体化,推行供应商寄存、实物储备和 协议库存 联合供应模式,压缩客户用电接入用时. No user access for external projects should take no more than
5 working days (all is the time taken by the power supply company);
customers with outside lines who do not need road excavation will not spend more than
20 working days (all for the power company);
The access time for users who need to excavate roads for outside projects shall not exceed
35 working days (the time for power supply companies shall not exceed
20 working days, and the time for government use shall not exceed
15 working days). The power supply company is the main organization for the customer in terms of project implementation, takes charge of the relevant procedures throughout the entire process, and provides one-stop service for the customer. The company'
s power grid construction investment extends to the customer'
s power meter, and the expenses are listed in the company'
s new customer development of the supporting power grid infrastructure project package or technological transformation project package. The approval authority and related system operation authority of all links involved in low-voltage customer reporting are all decentralized to the power supply company. The project is approved by the power supply company and reported to the company for record, and the approval of the project, the release of the plan, and the implementation of a power supply unit within the project are transferred. The integration of external line design selection and the initial feasibility study for approval will be promoted. The joint supply model of supplier storage, physical storage, and protocol inventory was implemented to reduce the time needed for electricity connection.
四、主要措施 4. Major Measures 1.落实客户 三个一 服务要求 (1) Three ones service requirements 供电公司履行 一口对外、一证受理、一站服务 三个一服务,落实客户告知程序;
供电公司为业扩配套项目实施主体,全程代办相关手续,为客户提供一站式服务,低压客户办电环节压缩至两个环节.新装、增容低压客户全部实现费控. The power supply company provides Three-ones Service -- One external communication, One license acceptance, One-stop service and implements the customer notification process;