World Bank Loan Project Environment Management Program (EMP) of Urban Centralized Heating Supply Engineering (Heating Supply Plant) for Ling Yuan City 凌源市城市集中供热工程(热源厂) 世行贷款项目环境管理计划(EMP) Prepared by: Environment Science Academy of Chaoyang City November.

2013 E1714 V16 REV Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized CONTENTS

1 Introduction

4 1.1 Project background.4 1.2 Name, nature and location of the project

5 1.3 Construction items of the project

5 2 Basis of compilation…7 2.1 Executive standard.7 2.2 Basis of compilation.10 3.Pollutant discharge…10 3.1 Waste water.10 3.2 Solid waste.10 3.3 Replacement of pollutant discharge and area pollutant increase/decrease situation

11 4 Analysis of environment impact…0 4.1 Current environment quality

0 4.2Analysis of environment impact in operation period.2 4.3 Analysis of environment impact in construction.2

5 Relieving measures for environment impact

7 6 Organization arrangement…10 7. Mornitoring schedule…11

8 Report policy…12 8.1Mornitor report.12 8.2 Recordand EMP operation yearly report.13

9 Training schedule…13

10 Public involvement in the implementation of the project…………

14 10.1 Public participation plan.ERROR! BOOKMARK NOT DEFINED. 10.2 Dispute and complain channel ..... ERROR! BOOKMARK NOT DEFINED.

11 Cost of implementing the management plan…17

1 Introduction 1.1 Project Background Ling Yuan City is located in the western border of Liaoning Province. Connecting to the north are Jian Ping County and Ning Cheng County, Inner Mongolia, to the northeast and east is Kazuo county, to the west and northwest is Ping Quan County of Hebei Province, to the southwest connects with Kuan Cheng County and Pingquan County of Hebei Province, to the south is connected with Jian Chang County and Qing Long County in Hebei Province, to the southeast is connected with Jianchang and Kazuo the two counties. The Geographical coordinates of Ling Yuan City is northern latitude 40° 35'

50 ~ 41° 26'

6 , east longitude 118°50'

20 ~ 119°37'

40 . The north and south inclined length is 93.3 kilometers long. The east and west width is 66.1 km, accounts for about 2.2% of the total area of the whole Province. The heating supply facility of Hong Ling Thermo Power Plant, the main heating resource of Ling Yuan City, has been in operation for many years and out of repair. The service of heating supply can'

t guarantee a normal operation for the past few years. The effect of heating supply from Hong Ling Power Plant is from bad to worse. In winter, the temperature in the most household is only about 12℃ and under 15℃ to the maximum. People'

s complains are heard everywhere with lots of unsatisfactory which influenced the people'

s livelihood of Ling Yuan City. And the urban construction area has been increasing with the continuing development of Ling Yuan City construction. The heating supply facility of Hong Ling Thermo Power Plant is aged that can'

t satisfy the increasing demand. New heating supply plant shall be urgently located and constructed somewhere at the circumference of Ling Yuan city center area as well as to construct heating supply piping network. Ling Yuan Antai Heating Supply Limited Liability Company was established in

2011 by the investment from municipal government with a main purpose of basically solving the heating supply problem in Ling Yuan City. After the establishment, Antai Heating Supply Company rented Hong Ling Thermal Power Plant to provide heating to the city. From July 2011, a heating source plant was built at the location of the old stadium of Ling Yuan City and to implement urban centralized heating supply in Ling Yuan City. The project can remove

25 small boiler houses and improving an area of 3.75 million square meters of heating supply condition, finally to realize centralized heating supply capacity of

7 million m2 . The total heating supply design capability of the heating source plant is

2 x 29MW and

3 x 70MW,

5 hot water boilers. The project is divided into two phases. The first phase of a 2x29MW reciprocating grate boiler is already in production in November

2011 and the second phase of

3 x 70MW reciprocating grate boiler shall be in operation from

2013 to

1015 according to the continuous expansion conditions of the urban heating supply areas. At present, most of the buildings in Ling Yuan City are heating supplied by dispersed small and medium-sized boiler houses which are low efficient in heating supply with more chimneys. Most of the dust removal equipment is ceramic multi-tube dust cleaners with low efficient dust removal and without desulfurization function. It is heavily polluted. Those boiler houses intermittently provide heating supply wasting lots of energy. It not only causes heavy pollution to the urban environment and increases the transportation of coal, ash and slag amount which imposes pressure to the municipal traffic and pollution from the transport vehicle emission, but also it occupies a lot of land and urban green areas for construction which seriously affects the city landscape and environmental quality of Ling Yuan City. In the presence of the above-mentioned problems, the construction of thermo power co-generation heating supply or large heating source plant for central heating supply to replace the dispersed heating boiler houses is the inevitable choice for the development of the city. After the implementation of this project, the paid heating source from the plant for centralized heating supply can replace the dispersed small coal-fired boiler houses, It can greatly improve heating efficiency and save energy, to reduce land occupation and solve problems of pipeline corrosion by unsatisfied water quality requirements, to limit water leakage rate in the reasonable range, to reduce dust, SO2, NOx, CO2 emissions. At the same time it also reduces the quantity of coal, slag transportation, traffic pressure and automobile exhaust. Thus it can improve the urban environment conditions. 1.2 Name, nature and location of the project Project name: Centralized heating supply engineering project of Ling Yuan City Location of construction:Planning area of Ling Yuan City Nature of construction:New construction 1.3 Construction items of the project The area of the engineering project includes 31.03 km of the first-class heating water network and

57 heating exchanger stations, out of which

23 stations were modified from the old heat-exchange stations,

31 newly-built stations and

3 new building heating supply stations within the urban overall plan boundary of the east of Hong Shan Road (101 National Highway) in Ling Yuan city, west of Gao-Lian route, south of Ling Gang steel, and north of Dalinghe River. Ling Yuan Xin-xing complex building,

37213 O, is selected as the building heating supply exchange station test point as the heat meter (building meter)installation area. The environment protection equipment of Antai Lingbei Thermo Power plant and Antai Heating Source plant shall be up-grade constructed. This project can realize a

7 million square meters of central heating supply area including the current heating supply area of 3.75 million square meters. The total investment of the project is

252 million yuan of which $20 million (about 131.05 million yuan) will be financiered from the World Bank loan. Antai Heating Source Plant: The first phase of a

2 x 29MW reciprocating grate boiler is already in production in November

2011 and the second phase of

3 x 70MW reciprocating grate boilers shall be in production in November

2013 See coal quality analyses report in Table 1-1. Table 1-1 Coal Quality Analyses Report Name Industrial analyses Element analyses water % Ash % Volatile % Heating value KJ/Kg sulfur % Carbon % Hydrogen % Oxygen % Nitrogen % Coal sample 21.6 29.34 25.44

16030 0.43 48.55 2........